Construction type/size
Foundation & Structural Steel
for 1,600 Ton Stamping Press

Design & Construction Location
Somerset, KY

Owner/client
Toyotetsu America, Inc.

Construction cost
$ 560,000

Delivery method
Design/Build

Schedule
Less than 3 months

 

Toyotetsu America, Inc.
1600 Ton Press Foundation

This project is a demonstration of the efficiency of the Design/Build process. Bristol Group engineered and self-performed excavation, concrete and structural steel for this 1600 ton transfer press foundation. The schedule was maintained in spite of the discovery and correction of unsuitable backfill conditions under the existing slab.

Other aspects of this project included the design and drilling of caissons, construction of a conveyor pit, electrical work and water piping and the extension of an existing concrete mezzanine. The project was completed in 76 days, 8 days ahead of schedule.

Copyright 2008 - All rights reserved.  All material presented on this web site is the sole property of Bristol Group, and cannot be copied without written authorization from Bristol Group Inc.