BUILDING TYPE
Conventional Steel Building

LOCATION
Versailles, Kentucky

OWNER/CLIENT
YH America, Inc.

CONSTRUCTION COST
$1,320,000

DELIVERY METHOD
Design / Build

SCHEDULE
Fast track- 6 months
Design & Construction

 

YH AMERICA, INC.  2004 BUILDING EXPANSION

YH America, Inc. began operations at its Versailles Sealant Division in April of 1998. In only 5˝ short years, YH America had reached capacity in production, on-site storage, and available office space. The challenge was simple - design and construct a new office, quality control laboratory, warehouse, and production area without disrupting the on-going operations at the facility. The results…mission accomplished!

Begun during a wet, challenging winter, the project was completed on schedule and within budget. The administrative staff moved into their new office in June of 2004, and the new production equipment came on-line the following month.

Copyright 2008 - All rights reserved.  All material presented on this web site is the sole property of Bristol Group, and cannot be copied without written authorization from Bristol Group Inc.