YH America 2009 Warehouse Expansion

YH expansion 2009 570

YH America, Inc had reached capacity in on-site storage space at its Versailles Hose Division and was forced to lease space to continue production. 

Project Specs
Building Type and Size: Warehouse Expansion
Location: Versailles, KY
Owner/Client: YH America Inc.
Construction Cost: Less than $1,000,000
Delivery Method: Design/Build
Schedule: Fast Track, 6 Months; Design and Construction
Completion: 2009

 

Following a successful building expansion in 2004, YH America contacted Bristol Group to design and construct a 25,600 sf warehouse expansion without disrupting the on-going operations at the facility.

Construction began during a wet, challenging spring. The project was completed on schedule and within budget. YH occupied their new facility in August of 2009.