Topy Corporation Rim Line #3

Topy Rim Line web

The challenge of placing 12’ of fill in winter conditions was solved by Bristol’s site work crews. With minimal cost impact, shot rock was substituted and time was recovered to meet the owner’s production commitment. The project included site preparation, a 25,000 square feet warehouse addition, a new 10 ton overhead crane and rim line machine foundations in the existing facility.

Project Specs
Building Type and Size: Pre-Engineered Metal Building Addition, 25,000 square feet; Rim Line machine; foundations
Location: Frankfort, KY
Owner/Client: Topy Corporation, Kajima Construction Services
Construction Cost: Less than $1,000,000
Delivery Method: Design/Build
Schedule: 9 months
Completion: 2002

 

Bristol Group designed and provided construction management services for mechanical, electrical and fire protection trades on this project. It was completed one month ahead of schedule.