PROJECT
Civil/Site Construction

LOCATION
Lexington, Kentucky

OWNER/CLIENT
The Pike Company

CONSTRUCTION COST
$600,000

DELIVERY METHOD
Plan/Spec

SCHEDULE
2 Months
Expedited Pad Delivery




WAL-MART SIR BARTON WAY 

This project includes 240,000 cubic yards of excavation, silt basins, sinkhole remediation and fine grading for building pads and parking areas.

The project progressed despite winter conditions due to intelligent management of site cuts and fills, runoff and protection of the work areas.

Building pad areas were delivered ahead of contract milestone dates.