PROJECT
Civil/Site Construction

LOCATION
Lexington, Kentucky

GC CLIENT
Gioffre, Inc.

CONSTRUCTION COST
APPROXIMATE $500,000

DELIVERY METHOD
Plan/Spec

SCHEDULE
Expedited Pad Delivery
Phased completion




LOWE'S OF NORTHEAST LEXINGTON 

This project includes 240,000 cubic yards of excavation, silt basins, sinkhole remediation and fine grading for building pads and parking areas.

The project required tie-in to underground utility infrastructure being installed concurrently at an adjacent site. The pieces fit together as a result of diligent coordination and cooperation.