PROJECT
Municipal Landfill
50 Acres
LOCATION
Charleston, South Carolina
OWNER/CLIENT
County of Charleston
CONSTRUCTION COST
$6,408,799
DELIVERY METHOD
Plan/Spec Competitive Bid
SCHEDULE
Fast Track – 6 Months
Construction
|
|
BEES FERRY LANDFILL CLOSURE
This project involved the closure of a 50-acre landfill cell. The existing cover material was graded prior to placement of a 1.5 foot clay cap. An additional 1 foot of cover soil was placed to protect the clay and support vegetation. The Owner faced an impending closure deadline from state regulatory agencies, requiring an aggressive project schedule. Off-site materials were hauled at a rate exceeding 200 triaxle loads per day to keep the project on track.
This successful project proved Bristol’s site work capabilities on a remote site which presented both technical and operational challenges.


|